home about the product how it happens frequently asked questions contact us
 
Obtain a quote [figure 1]
  • Client supplies floor plans and elevations, a site survey/estimate of site slope and a soil test / information about soil type; and
     
  • CV Substructure Systems prepares indicative quote and forwards to client for consideration
Proceed to engineering [figure 2]
  • Client accepts quote – forwards acceptance and pays engineers fee to CV Substructure Systems;
     
  • If not already provided, client supplies soil test and 3 sets of working drawings;
     
  • Engineer prepares computations, project drawings and standard drawings and completes certificate of compliance. Engineer may alert CV Substructure systems to special requirements that impact the quotation; and
     
  • CV Substructure Systems prepares QMBA contractual documents with
    contract price.
Proceed to installation [figure 3]
  • Contracts exchanged between Client and CV Substructure Systems;
     
  • Job scheduled, allocated to an installation team, materials requirements are planned and supplied to installation team;
     
  • Client/Client’s builder completes 90∞ set-out at the site, installs “hurdles”, specifies building lines and provides datum for finished floor height/s; and,
     
  • Client/Client’s builder provides information about the location of under ground services at the site.
Installation – foundation. All functions performed
by CV Substructure Systems’ installers [figure 4]
  • String the building area to determine the location of posts specified on the foundation plan;
     
  • Position Mega Anchor mainframes in the correct locations; and
     
  • For each foundation location:
     
    • Select appropriate orientation of mainframe for best appearance (may dig in on outside rows) and clearance for sub-floor plinths;
       
    • Use Installation Guide to align mainframe horizontally and vertically;
       
    • Drive piles of (at least) specified length – 3 for each mainframe – into the ground using an electric jackhammer with special driver head. Maintain vertical and horizontal alignment and ensure required frictional resistance achieved (note: installation into rock requires specialised equipment); and,
       
    • Remove installation guide and drive mainframe down to screw mainframe and lock with piles. Fix mainframe to piles with self-drilling
      Tec screws to form an integrated foundation unit.
       
Installation – risers and saddles. All functions performed
by CV Substructure Systems’ installers [figure 5/6]
  • Interpret plans to determine height/s of saddles relative to specified finished floor height/s;
     
  • Select diameter/s of riser appropriate for height/s;
     
  • Set up laser level; and,
     
  • For each post:
     
    • Use laser level to determine length of riser;
       
    • Cut riser to length, attach saddle, install to height with laser level accuracy and align with bearer run; and
       
    • Fix saddle to riser and riser to mainframe with specified number of Tec screws. Note: Variations on the standard system can be made available to suit non-standard posts.
       

Installation – bracing. All functions performed
by CV Substructure Systems’ installers [figure 7]
  • Interpret plans to determine extent of bracing required (as required for height and loading);
     
  • Measure and cut each brace to length;
     
  • Prepare each brace for fixing; and,
     
  • Fix bracing to riser/riser cap/bearer in accordance with bracing plan with Tec screws.

  o no concrete
o
no site preparation
o
no holes
o
no council delays
o
no excavator
o no mess
  Copyright (c) 2003 - CV Substructure Systems . Designed and Developed by Exigent Studios